Determination of Connection Cost
Home › Procedure and Criteria for Biomethane Production Unit access to the Distribution Networks of Enaon EDA › Determination of Connection Cost
Determination of Connection Cost
For the finalisation of the connection and determination of the connection cost, the Operator considers the shared use of infrastructure where multiple Biomethane Production Units are located in the area, alternative technical solutions, and the quality and quantity data of the biomethane to be injected.
Under Law 5215/2025, the cost of construction of the BMU and any required compression facility shall be borne exclusively by the Operator, whereas the cost of the connection pipeline shall be borne by the Producer.
The cost of the connection pipeline is allocated between the Operator and the Producer in the following cases:
- Distance of the Unit from the distribution network < 3 km: The cost of the connection pipeline shall be borne exclusively by the Operator.
- Distance of the Unit from the distribution network between 3–10 km: The cost of the connection pipeline for the section between 3–10 km shall be shared between the Producer and the Operator, each bearing fifty percent (50%) thereof.
- Distance of the Unit from the distribution network > 10 km: The cost of the connection pipeline beyond the initial 10 km length, for which the above cost-sharing mechanism applies, shall be borne exclusively by the Producer.
Depending on the circumstances, the option of connecting the Unit to the Distribution Network through a Virtual Pipeline or Virtual Interconnection may also be assessed.
In detail, the connection cost shall be determined as follows:
1. The cost of the connection pipeline (works, materials, TPI, supervision, contingencies) is calculated based on the information and sizing resulting from the simulations, as described in Chapter 3.
2. Where required, the detailed study is assigned to an external consultant. Indicative cases include:
- a. Long-distance extensions.
- b. Identification of special crossings requiring detailed investigation (river and canal crossings, motorways).
- c. Need for special studies (geotechnical studies, seismic protection).
- d. Routing through rural roads (usually unpaved roads), without clearly defined boundaries and with an evident error in the Cadastre.
- e. Routing along rural roads where Land Redistribution Acts have not been carried out by the competent Local Communities.
In such cases, the cost of the detailed study is included in the connection pipeline cost and follows the same cost-sharing mechanism described above. Where cost sharing applies (network-to-BMU distance > 3 km), the indicative cost of the connection pipeline is provided by the Operator to the prospective Producer, together with a construction schedule, within the procedure described in Chapter 5 (Step 2).
3. The cost is allocated between the Operator and the Producer in accordance with ar.9 of Law no.5215/2025.
4. The Connection Offer is prepared. Where costs are allocated to the Producer (connection pipeline > 3 km), the Connection Offer shall state that the final cost will be settled after completion of the works and on the basis of the supporting documents for the works executed. This procedure is necessary to address reasonable deviations and unforeseen costs that may arise during the construction stage.